On the first morning after the New Year, Golden Week or Obon (mid-August) holidays, the machine has lost its home position, air is leaking, the coolant has gone bad: most of these failures can be prevented by preparing before the holiday. Based on documents from machine makers such as Makino Technical Service, Brother Industries and Seiko Instruments, operating manuals from coolant and compressor makers, and Japan's Industrial Safety and Health Regulations, this page covers the schedule before the holiday, checklists by machine, batteries and data, coolant, what happens while the machine sits idle, the startup procedure and warm-up guide, common problems, and safety in order. You can tick the checklist on this page and print it as is. For daily inspection of each machine, see the Maintenance page.

What to do how many days before the holiday

From the night of the holiday to the morning after. What you prepare while the machine is stopped decides how well it starts up first thing in the morning (AI-made animated illustration; no sound).
  1. A few days ahead: condition the coolantRemove tramp oil, chips and sludge, and raise the concentration toward the upper end of the recommended range. Also take the sample for analysis.
  2. By the day before: batteries and dataReplace batteries that have not been changed in over a year, and save programs, tool offsets and parameters.
  3. Last day: clean, grease, rustproofBrush off chips, grease each axis and cycle it back and forth, and apply rust-preventive oil to bare table and fixture surfaces.
  4. Last day: park the axes and power offMove the axes to the position specified in the manual, remove the tool from the spindle, then switch off the power and put up a notice.

Start preparing the coolant a few days before the shutdown. Master Fluid Solutions says to remove tramp oil, chips and sludge, raise the concentration to the upper limit of the product's recommended range, and take the sample for analysis before shutdown[24]. Replace the batteries before the holiday starts. Makino Technical Service gives "before a long holiday" as the time to replace the absolute-position batteries, and says to do the regular replacement because inquiries pile up after a long holiday[6].

The final-day work is well summarized in Brother's "In preparation for long machine downtime". It has six items: grease each axis and run it through the full stroke about 3 times, remove the tool holder from the spindle, save the data, apply rust-preventive oil where rust is a concern, replace the batteries, and move each axis to the specified position before switching off the power[1]. The parking position differs by machine; Brother puts X and Y at the center of the stroke and Z at the top (so that, if the home position is lost to a dead battery, it can be adjusted from that position)[1]. Some makers, such as UNITED GRINDING for its grinders, specify "all axes to home"[4], so follow the operating manual for your own machine.

By machine: checklist before shutting down

A machining center table with chips brushed off and a thin film of rust-preventive oil
A table with chips brushed off and a thin film of rust-preventive oil on the bare surface. Remove the tool from the spindle too.Concept illustration(tap to enlarge)

Ticked items are saved in this browser (they are not shared with other people).

Machining centers

Lathes (CNC and manual)

Grinders

EDM machines

Compressors

Some overseas documents say "drain all the coolant" and "remove the grinding wheels", but those assume the machine will be down for several months. Documents from Makino (USA) and UNITED GRINDING separate a "full shutdown", assuming COVID-19 production stoppages, from a "partial shutdown" where people look in on the machine[3][4]. For one to two weeks at New Year, the basic approach is the partial shutdown: keep the fluid and condition it rather than draining (see "Coolant" below). For a shutdown of 30 days or more, Hurco also has a procedure of adding a rust inhibitor to the lube oil from the automatic lubricator and cycling all axes several times[5].

Batteries and data: so you do not lose the home position

Batteries inside an open control cabinet and a lamp showing that the power is on
Illustration of the batteries inside a control cabinet. Depending on the battery type, some are replaced with the power on and some after switching it off.Concept illustration(tap to enlarge)

The most common causes of a machine failing to start after being stopped for several months are loss of the home position due to dead batteries, and servo overload caused by caked grinding dust, says Seiko Instruments' maintenance newsletter[9]. When the power stays off for days the battery voltage drops, and the home position and CNC data can be lost, or a false detection can prevent a restart. Brother recommends replacing batteries before a shutdown if the machine will be stopped for a while and the batteries have not been changed for more than a year[2].

"Power on" depends on the battery typeAbsolute-position (encoder) batteries are replaced with the power on, because switching off loses the stored position. On the other hand, some batteries are replaced within a short time after switching the power off. The table below is based on Makino machines and similar; models and times differ by machine. Always follow the procedure in the operating manual.

BatteryWhen to replacePowerNotes from the documents
For absolute position (pulse coder / scale)Before a long holiday, every 2,000 hours of use or 1 year, or when a low-battery alarm appears (Makino)Leave on, after confirming that machine motion has stoppedSwitching off to replace loses the absolute position, and a manual home return is required[6]. For Brother's SPEEDIO as well, replace with the operation panel power ON[2]
Servo drive / CNC / robotBefore a full shutdown (UNITED GRINDING)Leave on[4]On Seiko Instruments grinders the servo amplifier battery lasts 5 years. The year of manufacture is printed on the side[9]
For NC backupBefore a long holiday, every year, or when an alarm appears (Makino)Follow the manual's procedureFinish within 30 minutes. If you switch off with the voltage still low and leave it for a week, memory is lost. Save all data in one batch before replacing[7]
For operation panel (PANEL i)Before a long holiday, every year (Makino)Switch off first; within 5 minutesTurn the power on for about 30 seconds, switch it off, and swap the battery within 5 minutes. Save all data in one batch before replacing.[8]

Saving data: Brother lists programs and the data bank[1]; Makino (USA) and UNITED GRINDING list machine data and CNC data (UNITED GRINDING also lists machining programs)[3][4]. If you save tool offsets, work coordinates and parameters too, you can reload them if data is ever lost. For the idea of tool offsets, see Work Offset and Tool Length Setup.

Do not let coolant go bad: condition it and keep it circulating instead of draining

Cross-section of a coolant tank pulled out beside the machine, with an oil skimmer removing tramp oil from the surface
Illustration of a cross-section of a coolant tank. When tramp oil on the liquid surface seals off the air, rot progresses over the holiday.Concept illustration(tap to enlarge)

Coolant smells after a holiday because the fluid does not move while idle, tramp oil forms a lid on the surface, and anaerobic bacteria multiply. Tramp oil, chips and sludge are food and shelter for bacteria and the main cause of the rotten smell[24]. Most water-soluble fluids are mildly alkaline at pH 8–10, and pH falls as spoilage progresses, so it is a guide for control[21].

WhenWhat to do
Before the holiday (from a few days ahead)Remove tramp oil, chips and sludge. Raise the concentration toward the upper end of the product's recommended range to increase pH buffering. Bring pH into range. Take the sample for analysis.[24]
During the holidayIf possible, run the pump to circulate the fluid[24]. Blaser says to circulate for at least 30 minutes every day during shutdown, keep the skimmer running (if there is none, remove tramp oil by hand), and run the chip conveyor before circulating to clear chips from the bottom[22][23]
After the holidayIn the tank, stir thoroughly, then check concentration and pH[1]. Also check the smell and color
  • How high to raise the concentration: Blaser says to keep at least 8% (by volume) during shutdown[22], but that is a value for its own products. Check the fluid maker's documents so you do not exceed the upper limit of the recommended range for the fluid you use
  • Whether to blow in air: Makers disagree. Yushiro Chemical says to avoid aeration as an anti-odor measure because it causes aerobic bacteria to multiply and pH to fall[21], and UNITED GRINDING says to run a circulation pump or aeration pump during shutdown[4]. When in doubt, make "circulation" the default and ask the fluid maker about aeration
  • Non-water-soluble (oil-based): Blaser says no special treatment is needed[22]

Daily concentration and pH measurement and how to recognize spoilage are covered on the Coolant management page.

What happens while the machine is idle

On a winter morning, water droplets and rust spots on the table of a cold machine
Illustration of a chilled table on a winter morning. Temperature differences cause water droplets, and rust can appear on bare surfaces.Concept illustration(tap to enlarge)
What happensCause / sourcePrevention
Home position and data are lostThe power stays off for days and the battery voltage drops[2]Replace batteries and save data before the holiday
Servo overload when movedOn machines using water-soluble grinding fluid, grinding dust around moving parts cakes on[9]Clean the inside of the machine before stopping. If stopping for long, warm up or dry-run one day a week (about 8 hours)[10]
Sudden stop with no alarmExample of rust forming on the ball screw after a long stop[11]Grease and run the full stroke before stopping[1]
Spindle life shortensAfter 1–3 days idle, the lubricant inside the spindle settles. Running at full speed without warm-up damages it[12]After the holiday, warm up before raising the speed
Chuck gripping force dropsRust inside the chuck[25]Pack with grease before stopping to prevent rust[25]
Drain freezesRisk of failure from drain freezing: ANEST IWATA reciprocating units at ambient 2 °C or below, Meiji Air Compressor Mfg. GN/GH types at 0 °C or below[14][15]When stopping, release all the tank air and drain completely[14]
Rust, condensationMakino recommends an installation environment of 10–40 °C room temperature and 35–70% humidity (no condensation)[16]Rust-preventive oil, covers. No document gave the temperature difference at which condensation occurs as a number

In summer breaks (Obon), heat and humidity become the problem instead. Hurco says that when the ambient temperature is 31 °C or higher, set the spindle chiller 5 °C below ambient to reduce condensation inside the spindle head[5].

Startup procedure after the holiday and warm-up guide

In a factory with morning sun, the spindle of a machining center with its door closed turns slowly to warm up
Illustration of warm-up after the holiday. With the door closed and no tool mounted, move the spindle and axes slowly.Concept illustration(tap to enlarge)
  1. Check the room temperatureIf it is thoroughly cold, turn on heating first and bring the room to temperature before switching on the power.
  2. Bring in the air slowlyStart the compressor, drain it, and open the machine-side regulator slowly from the closed position.
  3. Check oil, pressure and filtersCheck oil level, pressure, clogging and oil leaks. On machines with manual lubrication, lubricate before powering on.
  4. Power on and check alarmsCheck the alarms and battery indicator, then do home return. Some alarms appear only when it is too cold.
  5. Move the axes back and forth at low speedDo not go straight to rapid. Run each axis through the full stroke about 3 times at low speed.
  6. Run in the spindle in stagesRaise the speed little by little from a low rpm and let the spindle settle in with warm-up.
  7. Mix the coolant and measureStir thoroughly in the tank, then check concentration, pH and smell.
  8. Test cut and first-piece measurementMeasure the first piece and confirm the dimensions before moving on to production.

Makino Technical Service's "Checkpoints before restart" says that after starting the compressor you should raise the pressure to the specified value by opening the machine-side regulator a little at a time from closed; after switching on power and air, check oil level, pressure, filter clogging and oil leaks; check the spindle seal, wiper and taper (clean the taper with a cleaning fixture, not an air gun); and if the room has cooled, bring it up to temperature before powering on. Applying pressure all at once cracks the regulator bowl and auto drain, and running the pump with no oil damages the unit[16]. Hurco also has a procedure for machines with a manual lubrication plunger: pump it 3–6 times before switching on the power[5].

After a holiday, run the spindle at a speed raised in stages from a low rpm. Brother says to move each axis through the full stroke at low speed about 3 times, then run in the spindle starting at 500 min⁻¹ and stepping every 5 minutes through 500 → 1,000 → 2,000 → 4,000 → 6,000 → … up to maximum speed[1]. As a reference example of warm-up, Makino cites moving all axes at about S1000 and F1000–F2000 for about 30 minutes (noting that this is not warm-up for high accuracy)[16].

Up to 60 minNot needed60 min–48 h5 min 30 s2–7 days32 min 30 sOver 7 days56 min 30 sTime the spindle was stopped → total pre-lubrication and warm-up time (example: Hurco high-speed motor spindle, 6,000–18,000 min⁻¹)
The longer it was stopped, the longer the warm-up. A break longer than one week at New Year falls in the longest tier.[5].
SourceTime stoppedWarm-up / run-in
Hurco (high-speed motor spindle)60 min–48 h / 2–7 days / over 7 daysTotal pre-lubrication and warm-up 5 min 30 s / 32 min 30 s / 56 min 30 s. Until finished, manual spindle start and automatic operation are not possible[5]
Hurco (spindle)Over 30 daysRun in following the order in the table. The bearing area must not exceed 55 °C[5]
Haas (live tooling on CNC lathes)Over 4 days / 2 weeks or more20-minute warm-up (250–5,000 min⁻¹, 200 s each) / 2-hour run-in[13]
Makino (machining center)After a long stop / right after startupAbout 30 minutes at about S1000 and F1000–2000 (reference example)[16]
Brother (SPEEDIO etc.)After a long shutdownFrom 500 min⁻¹, stepping every 5 minutes up to maximum speed[1]

Until dimensions settle takes even longer. A research report of the Machine Tool Engineering Foundation says it is commonly accepted that machines generally need at least 2 hours after starting operation to become thermally stable, and 20–120 minutes of dry running to suppress thermal deformation[19]. Makino turns the power on at least 3 hours before measuring accuracy and runs a fixed program for 30 minutes before measuring[17]. After a holiday the whole machine is stone cold, so if the first-piece dimensions are off, first suspect insufficient warm-up. Thermal growth can be checked with the thermal expansion calculator.

Common problems after the holiday and what to do first

A packaged compressor and air tank. Water is being drained from the drain valve under the tank
Illustration of a compressor and air tank. After the holiday, drain first, then send air to the machine slowly.Concept illustration(tap to enlarge)
SymptomCommon causeWhat to do first
Alarm demanding home return / absolute position alarmAbsolute-position battery is dead[6]Replace the battery and do a manual home return. If data was lost, restore the saved data
Stops because of an air leakThe auto-drain cup or fittings in the air dryer deteriorate and crack[18]. Applying pressure all at once cracks the bowl[16]Find the leak and replace the cracked cup. Open the regulator slowly
Alarm for stopped cooling fan of the heat sinkThe fan fails from years of dirt[18]Clean or replace it. Note the servo amplifier display and model and contact the maker
Oil temperature / coolant alarm at power-onIn some cases the room is cold and the oil or coolant has gotten too cold[16]Raise the room temperature, then reset
Servo overload when movedGrinding dust or chips caked on[9]Clean, then move at low speed
Compressor will not turn or pressure will not buildSeizing or valve condition after a long stopAtlas Copco says to turn the coupling by hand with the power off to check that it turns freely, and to open the discharge valve slowly to match the piping pressure before starting[20]

For compressors, ANEST IWATA's manual for its reciprocating units says that if stopped for a week or more, drain once a week and run unloaded for 30 minutes every month. For leak checking, hold maximum pressure for 30 minutes and check that the pressure drop is within 10% of maximum pressure[14]. For screw compressors, follow the manual for your model. For routine inspection, see the compressor maintenance page.

Safety: test runs, signals and lockout

A surface grinder with a wheel guard running idle in a test run
Illustration of a test run of a grinding wheel. Run it with the guard in place and do not stand in front of the wheel.Concept illustration(tap to enlarge)

The big clean before a holiday and the restart after it are periods with many non-routine tasks. The Japan Industrial Safety and Health Association (JISHA)'s year-end and New Year zero-accident campaign lists simultaneous inspection of machinery and pre-work checks, and safety confirmation when work resumes in the new year. For inspection and repair, it says to shut off power and stop completely, post a sign such as "Inspection in progress: do not operate" near the control panel, and restore any safety devices that were disabled and covers that were removed[29] (the campaign period is set each year, so check the latest guidelines).

Japan's Industrial Safety and Health RegulationsDetailsWhere it applies around a holiday
Article 107When cleaning, oiling, inspection or repair is hazardous, stop the machine, lock the starting device and post a sign, etc.[28]Cleaning and greasing before the holiday, inspection after
Article 104If starting operation is hazardous, set a signal and designate the person who gives it[28]Starting up after many people have inspected
Article 118Grinding wheels must be test-run for at least 1 minute before work starts that day, and at least 3 minutes after replacement[28]First work of the day after the holiday. A wheel removed and refitted during the holiday needs 3 minutes or more
Article 117Rotating grinding wheels must have a guard (except under 50 mm diameter)[28]Forgetting to refit guards removed for cleaning
Article 136Presses must have the clutch, brake, emergency stop and so on inspected before work starts that day[28]When the factory has presses

Replacing grinding wheels and test-running them is done by people who have received special training (required by law). For grinder inspection, see the grinder maintenance page; precautions for starting hydraulic units (start the pump unloaded and check the rotation direction; milky oil means water contamination) are in Nachi-Fujikoshi's materials[26].

FAQ

Even for a break as short as New Year, should I drain the coolant?
For one to two weeks, the basic approach is to keep it and condition it. Remove tramp oil, chips and sludge, raise the concentration toward the upper end of the recommended range, and if possible keep circulating it during the break[24][22]. The drain-everything procedure is an example for a "full shutdown" of several months[3][4].
When should I replace batteries? Should the power stay on?
Replace them before the holiday begins. Some documents recommend replacement if they have not been changed in over a year[2]. Absolute-position batteries are replaced with the power on, but some, such as those for the operation panel, are replaced within a short time after switching the power off[6][8]. Always follow the procedure in your machine's operating manual.
About how many minutes should warm-up take after the holiday?
The machine's operating manual takes priority. As examples, Makino cites about 30 minutes at about S1000 and F1000–2000[16], and for Hurco's high-speed spindle, 5 min 30 s to 56 min 30 s depending on the time stopped[5]. Until dimensions settle, about 2 hours is generally said to be needed[19].
Is a 1-minute grinder test run still enough after a holiday?
Before work starts that day it is at least 1 minute, and at least 3 minutes when a wheel has been replaced (Japan's Industrial Safety and Health Regulations, Article 118)[28]. If a wheel was removed and refitted during the holiday, run it for 3 minutes or more as for a replacement.

Inspection items for each machine are covered in the Machining centers / lathe / Grinders / EDM machines / Compressors maintenance pages.

Sources

  1. Brother Industries, "In preparation for long machine downtime" (2022 edition)
  2. Brother Industries, "Battery replacement before long machine downtime" (May 2020)
  3. Makino Inc. (USA), "Machine layup suggestions" (2020-03-23)
  4. UNITED GRINDING, "Quick Guide: Shutdown Procedures for Grinding Machines" (2024-11-14)
  5. Hurco, "Maintenance and Safety Manual for i-Series Machines v573EN"
  6. Makino Technical Service, "Battery replacement: for absolute pulse coder / scale"
  7. Makino Technical Service, "Battery replacement: for NC backup"
  8. Makino Technical Service, "Battery replacement: for PANEL i"
  9. Seiko Instruments, Precision Machinery Division, Maintenance News No. 32 (2020-10-15)
  10. Seiko Instruments, Precision Machinery Division, Maintenance News No. 33 (2021-02-01)
  11. Seiko Instruments, Precision Machinery Division, Maintenance News No. 4 (2011-05-12)
  12. Haas Automation Ltd (UK), "Looking After Your Spindle"
  13. Haas, "SL - Live Tooling - Operation" (machines from 2001–2010)
  14. ANEST IWATA operating manual, reciprocating compressor package type CLP15EF–110EF
  15. Meiji Air Compressor Mfg. operating manual, GN/GH types (revised August 2016)
  16. Makino Technical Service, "Checkpoints before restart"
  17. Makino Technical Service, "Warming up machine tools"
  18. Makino Technical Service, "Examples of failures likely after long holidays"
  19. Machine Tool Engineering Foundation, research project RU-22, "Thermal deformation reduction design with zero warm-up time"
  20. Atlas Copco, "Advice for stopping and restarting air compressors"
  21. Yushiro Chemical Industry, metalworking fluids FAQ
  22. Blaser Swisslube, "What to do with your metalworking fluid during longer production stops?"
  23. Blaser College, "Management of water-miscible cutting fluids during production stoppage" (in Spanish, 2020-04-15)
  24. Master Fluid Solutions, "Preparing Your Sump for a Temporary Shutdown" (2020-04-17)
  25. Kitagawa power chuck BR series operating manual
  26. Nachi-Fujikoshi standard hydraulic unit catalog, "For safe use of hydraulic equipment and systems"
  27. FANUC Europe, "ROBOCUT Preventive Maintenance"
  28. Industrial Safety and Health Regulations (e-Gov Law Search), Articles 104, 107, 117, 118 and 136
  29. Japan Industrial Safety and Health Association (JISHA), "FY2024 (Reiwa 6) Year-End and New Year Zero-Accident Campaign Guidelines"

More articles