Cycle time and cost estimator
Add one row per operation to get the total cutting time, the time per part including setup and loading, and a rough machining cost from your shop rate (machine plus operator cost per hour). Good for a first quote or for comparing process plans.
Operations
| Operation | Dia. D mm | Vc m/min | Feed | Flutes | Length L mm | Passes | Time |
|---|
Setup, batch and shop rate
Turning, drilling: Vf = f × n; milling: Vf = fz × flutes × n (n = 1000 × Vc ÷ (π × D))
Operation time = L ÷ Vf × passes; tapping goes in and out, so × 2
Per part = cutting time + loading + setup ÷ batch size
How to use it
- Pick one row per operation: OD/ID turning, drilling, tapping or milling/end mill. Add rows with “+ Add operation” and remove them with ×.
- Enter diameter D, cutting speed Vc, feed, length L and passes. D is the diameter being cut for turning, the drill diameter for drilling, the nominal size for tapping and the tool diameter for milling. Feed is f per revolution (mm/rev) for turning and drilling, the pitch (mm) for tapping and fz per tooth (mm/tooth) for milling; only milling uses the number of flutes.
- L is the distance the tool feeds while cutting, for one pass. Use passes for the number of turning passes over the same length, or for the number of identical holes when drilling or tapping.
- Enter the setup time (once per batch), the non-cutting time (every part), the batch size and the shop rate.
- The results are the cutting time per part, the time per part with the setup shared across the batch, the batch total and the rough cost. The right-hand column shows the time for each operation on its own.
Worked example: the three default operations
The defaults are OD turning (D 40 mm, Vc 150 m/min, f 0.2 mm/rev, L 60 mm, 3 passes), drilling (D 8.5 mm, Vc 80 m/min, f 0.15 mm/rev, L 25 mm, 4 holes) and tapping (M10, Vc 10 m/min, pitch 1.5 mm, L 20 mm, 4 holes).
- Turning: n = 1000 × 150 ÷ (π × 40) ≈ 1,194 rpm, Vf = 0.2 × 1,194 ≈ 239 mm/min. One pass is 60 ÷ 239 ≈ 0.25 min, so 3 passes take about 45 s.
- Drilling: n ≈ 2,996 rpm, Vf ≈ 449 mm/min. One hole is 25 ÷ 449 ≈ 0.056 min, so 4 holes take about 13 s.
- Tapping: n ≈ 318 rpm, Vf = 1.5 × 318 ≈ 477 mm/min. Doubled for in and out, 4 holes take about 20 s.
- The cutting time totals about 1 min 19 s. Adding 1 min of loading and 30 min setup ÷ 10 parts = 3 min gives about 5 min 19 s per part. At a shop rate of 6,000 per hour, 5.31 ÷ 60 × 6,000 ≈ 531 per part, or about 5,312 for the batch of 10.
Reading the result: here cutting is only about a quarter of the time per part; more than half is the share of the setup. With a batch of 100 the setup share falls to 0.3 min and the time per part to about 2 min 37 s (about 261). Making a single part takes about 32 min 19 s (about 3,231). For small batches, how you count setup and loading changes the price far more than fine-tuning the cutting data.
Worked example: adding a milling operation
The row added by “+ Add operation” is an end mill, D 10 mm, Vc 120 m/min, fz 0.05 mm/tooth, 4 flutes, L 100 mm, 2 passes. n = 1000 × 120 ÷ (π × 10) ≈ 3,820 rpm and Vf = 0.05 × 4 × 3,820 ≈ 764 mm/min, so one pass is 100 ÷ 764 ≈ 0.13 min and two passes about 16 s. Because milling multiplies by the number of flutes, a 2-flute tool at the same fz halves the feed rate and doubles the time.
Time that estimates tend to miss
- Rapid moves: approaching and leaving the work and moving to the next hole. They grow with the number of holes.
- Tool changes: the ATC (automatic tool changer) change time is given in the machine specifications. Add number of tools × change time to the non-cutting time.
- Approach and run-out: the tool moves at feed a little before it starts cutting. Put the approach and run-out distances moved at feed into L as well as the cut length. For drills, add the point length (about 0.3 × D for a 118° point); for a face mill passing right across the part, add the tool diameter.
- Spindle start, stop and reversal: a tap reverses at the bottom of the hole. This calculator assumes the return is at the same feed rate and multiplies by 2.
- Measuring, deburring, clearing chips and proving the program on the first part: put work done while the machine waits into the non-cutting time if it happens every part, or into the setup time if it happens once per batch.
When the diameter changes in turning
Within one row the calculator assumes the same diameter and spindle speed. When an OD is turned in several passes, each pass is at a smaller diameter; with constant surface speed (G96) the spindle speed rises and so does the feed rate. If roughing and finishing differ in diameter or cutting data, enter them as separate rows or use the mean diameter of that operation. For facing, where the diameter changes a lot, the mean diameter gives a rough time (it will be longer if the spindle hits its speed limit).
FAQ
- What is the difference between cycle time and takt time?
- Cycle time is the time it actually takes to make one part. Takt time is the time you can spend per part to meet demand: available working time ÷ quantity required. If the cycle time is longer than the takt time, you cannot make the quantity in time. This calculator gives the cycle time (and the time with setup shared out).
- What goes into the shop rate?
- Machine costs (depreciation, power, maintenance), operator wages and factory overheads, spread over one hour. It depends on the size and type of machine and how many machines one person runs, so use your own figure.
- Why does the calculated time not match the real cycle time?
- Usually because rapid moves, tool changes and approach and run-out distances are missing. Time a real part once and put the difference into the non-cutting time; you can then reuse it for similar parts. Running with the feed or spindle override turned down also makes it longer.
- Where should I look first to cut the time?
- Look at the time per row and start with the longest operation. Cutting time is L ÷ Vf, so fewer passes, a higher feed or a tool with more flutes all help (within the tool maker’s recommendations). For small batches, as the worked example shows, reducing setup time does more for the time per part.
Notes
- Rapid moves, tool changes and approach distances are not included, so a real cycle time will be longer. Add an allowance to the non-cutting time.
- Shop rates vary a lot between companies, machines and regions. Enter your own; the default is only an example.
- Material, heat treatment, finishing, inspection and shipping are not included.