Cycle time and cost estimator

Add one row per operation to get the total cutting time, the time per part including setup and loading, and a rough machining cost from your shop rate (machine plus operator cost per hour). Good for a first quote or for comparing process plans.

Operations

OperationDia. D mmVc m/minFeedFlutesLength L mmPassesTime

Setup, batch and shop rate

Cutting time (per part)1 min 19 s
Per part (incl. share of setup)5 min 19 s
Total for the batch53 min 08 s
Rough cost (per part)8
Rough cost (batch)80

Turning, drilling: Vf = f × n; milling: Vf = fz × flutes × n (n = 1000 × Vc ÷ (π × D))
Operation time = L ÷ Vf × passes; tapping goes in and out, so × 2
Per part = cutting time + loading + setup ÷ batch size

How to use it

  1. Pick one row per operation: OD/ID turning, drilling, tapping or milling/end mill. Add rows with “+ Add operation” and remove them with ×.
  2. Enter diameter D, cutting speed Vc, feed, length L and passes. D is the diameter being cut for turning, the drill diameter for drilling, the nominal size for tapping and the tool diameter for milling. Feed is f per revolution (mm/rev) for turning and drilling, the pitch (mm) for tapping and fz per tooth (mm/tooth) for milling; only milling uses the number of flutes.
  3. L is the distance the tool feeds while cutting, for one pass. Use passes for the number of turning passes over the same length, or for the number of identical holes when drilling or tapping.
  4. Enter the setup time (once per batch), the non-cutting time (every part), the batch size and the shop rate.
  5. The results are the cutting time per part, the time per part with the setup shared across the batch, the batch total and the rough cost. The right-hand column shows the time for each operation on its own.

Worked example: the three default operations

The defaults are OD turning (D 40 mm, Vc 150 m/min, f 0.2 mm/rev, L 60 mm, 3 passes), drilling (D 8.5 mm, Vc 80 m/min, f 0.15 mm/rev, L 25 mm, 4 holes) and tapping (M10, Vc 10 m/min, pitch 1.5 mm, L 20 mm, 4 holes).

Reading the result: here cutting is only about a quarter of the time per part; more than half is the share of the setup. With a batch of 100 the setup share falls to 0.3 min and the time per part to about 2 min 37 s (about 261). Making a single part takes about 32 min 19 s (about 3,231). For small batches, how you count setup and loading changes the price far more than fine-tuning the cutting data.

Worked example: adding a milling operation

The row added by “+ Add operation” is an end mill, D 10 mm, Vc 120 m/min, fz 0.05 mm/tooth, 4 flutes, L 100 mm, 2 passes. n = 1000 × 120 ÷ (π × 10) ≈ 3,820 rpm and Vf = 0.05 × 4 × 3,820 ≈ 764 mm/min, so one pass is 100 ÷ 764 ≈ 0.13 min and two passes about 16 s. Because milling multiplies by the number of flutes, a 2-flute tool at the same fz halves the feed rate and doubles the time.

Time that estimates tend to miss

When the diameter changes in turning

Within one row the calculator assumes the same diameter and spindle speed. When an OD is turned in several passes, each pass is at a smaller diameter; with constant surface speed (G96) the spindle speed rises and so does the feed rate. If roughing and finishing differ in diameter or cutting data, enter them as separate rows or use the mean diameter of that operation. For facing, where the diameter changes a lot, the mean diameter gives a rough time (it will be longer if the spindle hits its speed limit).

FAQ

What is the difference between cycle time and takt time?
Cycle time is the time it actually takes to make one part. Takt time is the time you can spend per part to meet demand: available working time ÷ quantity required. If the cycle time is longer than the takt time, you cannot make the quantity in time. This calculator gives the cycle time (and the time with setup shared out).
What goes into the shop rate?
Machine costs (depreciation, power, maintenance), operator wages and factory overheads, spread over one hour. It depends on the size and type of machine and how many machines one person runs, so use your own figure.
Why does the calculated time not match the real cycle time?
Usually because rapid moves, tool changes and approach and run-out distances are missing. Time a real part once and put the difference into the non-cutting time; you can then reuse it for similar parts. Running with the feed or spindle override turned down also makes it longer.
Where should I look first to cut the time?
Look at the time per row and start with the longest operation. Cutting time is L ÷ Vf, so fewer passes, a higher feed or a tool with more flutes all help (within the tool maker’s recommendations). For small batches, as the worked example shows, reducing setup time does more for the time per part.

Notes